A section of towpath linking west Oxford with Folly Bridge is about to be closed as work gets under way for the construction of a £14m new river bridge.
The Oxpens River Bridge, which will link Oxpens Meadow to Grandpont Nature Park, was backed by the city council in 2024.
Campaigners against the bridge launched a judicial review into the decision which was dismissed by the High Court on all five counts.
READ MORE: River bridge project moves into construction
The bridge was initially expected to cost £10.3m but the city council now estimates it will cost £14m.
The bridge is designed to improve access between the city centre and surrounding areas for pedestrians and cyclists.
An artist's impression of the new Oxpens river bridge (Image: Contributed)
Work began earlier this summer, with Jackson Civil Engineering currently preparing the site for construction.
Diggers can now be seen on the riverbank, and signs have been erected to warn people of the impending closure and diversions, from October 19.
A closure notice on the towpath in Oxford (Image: Andy Ffrench)
A spokesman for the city council said: "There is a Temporary Traffic Regulation Order in place to close the towpath through Grandpont Nature Park to enable work on the Oxpens River Bridge project. The closure does not extend as far as Osney Lock or Folly Bridge.
"A signed diversion route will be available through Grandpont while the towpath is closed.
"Work will begin next week to relocate a cable that runs along the towpath. This requires trenches to be excavated, meaning the towpath must be temporarily closed to ensure public safety.
"Further information about the bridge works and associated footpath closures is available on the council's website: https://www.oxford.gov.uk/building-projects/oxpens-river-bridge
One sign says a section of the towpath at the nature park will be closed for 56 weeks from October 19.
The new bridge is a key part of the Oxford West End regeneration programme, which aims to create a vibrant district focused on sustainable transport and green infrastructure.
A towpath closure is expected in Oxford (Image: Andy Ffrench)
By improving walking and cycling links, the bridge is expected to help reduce car dependency, lower carbon emissions, and offer more sustainable travel options for residents.
City councillor Susanna Pressel said: "This is an exciting project, which will provide an attractive, safe and much faster route for pedestrians and cyclists from West Oxford to the city centre.
“It was silly of the contractors to say that the Thames towpath and the path alongside Gibbs Crescent will be closed for 55 weeks. It should have said up to 55 weeks.
City councillor Susanna Pressel (Image: Contributed)
"It will almost certainly be far less than this. The bridge should be in place and all the paths reopened by next spring. Most of the signs they put up were premature as well.”
“In fact, the river towpath is still open now, although it will need to close next week.
"The upper path will remain open for the time being. When both are closed, there is a diversion nearby.”