A huge dredging project to save the ‘finest view in England’ has reached a major milestone at Blenheim.

Decades of silt build-up has left the Queen Pool at risk of drying out completely.

A flotilla of floating diggers has carefully removed 100,000 cubic metres of silt from the lake – marking the first stage in the epic nine-month rescue mission.

The dredge is believed to be one of the largest civil engineering projects ever undertaken at a UK heritage site.

Oxford Mail:

Leading wet civil engineering contractor, Land & Water will eventually remove 300,000 cubic metres of silt, enough to fill Wembley Stadium, and return the ‘Capability’ Brown-designed lake to its original depth of two metres from its current shallows of 30cm.

READ ALSO: Police warn residents after man seen acting suspiciously around estate

Dubbed the finest view in England by Winston Churchill’s father, the vista across the lake and over the Vanbrugh-designed Grand Bridge to the 18th century Baroque Palace is under serious threat of disappearing.

Blenheim Estate director Roy Cox said: “The Queen Pool is an iconic part of the World Heritage Site, it’s a SSSI, a fishery and a national treasure seen by over a million people each year.

“Over 70 per cent of the lake now has a depth of just 30cms or less. It is silting up at a rate of one to two centimetres per year but, during severe storms, deposits can reach up to 20cm.

“Without this drastic intervention the Queen Pool would revert to a wetland in the next 5-10 years and the nation’s ‘Finest View’ will be lost,” he added.

Floating diggers move slowly across the full surface of the lake, dredging over the course of about nine months. Along with the diggers are six hoppers which go backwards and forwards, bringing the silt from the platform to land.

This removed silt is being relocated to an area of the estate known as Great Park to create a new 16-hectare grassland mound.

Oxford Mail:

Land & Water's Project Manager Charlie Oakes said: “We are thrilled to have reached the 100,000m3 milestone. The Blenheim project has been an incredible undertaking and we have valued the chance to work on such an iconic landscape.

READ ALSO: Revealed: most popular baby names in Oxfordshire

"We are now a third of the way through our dredging journey at Blenheim Palace, with the final dredge anticipated to finish early next year,” he added.

The last major dredging operation was in 1895-1897 when 150,000m3 of silt was removed.

Queen Pool is the upper lake at Blenheim and was created by ‘Capability’ Brown around 1763 as part of his extensive re-landscaping of the Park and Gardens. 

The man-made lake gets its name from a 14th century fish pool that was known to be a favourite place of Queen Philippa, wife of Edward III.

 

The Dredge by numbers

Total lorry loads to date– 10,707

Lorry load in m3 – 9.4

Tonnes – 150,968.7

Volume of silt removed (m3) to date – 100,645.8

Days dredging – 93

Average volume (m3) of silt remover per day – 1,082

Average truck loads deposited per day - 115

 

 

 

A message from our Editor

Thank you for reading this story and supporting the Oxford Mail.

If you like what we do please consider getting a subscription for the Oxford Mail and in return we’ll give you unrestricted access with less adverts across our website from the latest news, investigations, features, and sport.

Follow us on Facebook, Twitter, Instagram and Tik Tok for more. 

You can also join the conversation in our Facebook groups: stay ahead of traffic alerts here, keep up to date with the latest from court here, share your favourite memories of Oxford here, get your daily dose of celebrity news here and take some time out with news that will make you smile. 

If you’ve got a story for our reporters, send us your news here. You can also list an event for free here.