MEASURES will be taken to manage costs rather than find extra money if inflation further affects a major new roads project in Didcot

The HIF1 programme, a combination of four projects to ensure there is capacity to connect 12,000 houses set to be built to the south of Oxford, has been mired in controversy on environmental and cost grounds.

More than £50 million extra has had to be found and almost £30 million of that is being borrowed by Oxfordshire County Council with opponents questioning whether the bill could get even bigger as inflation spirals. 

READ MORE: HIF1 programme set to be approved at next planning stage

The council’s latest report stated that £26.653 million had been allocated to deal with inflation within the increased budget of £296.155 million.

Councillor Charlie Hicks said discussions with the county’s cabinet member for finance, Councillor Calum Miller, suggested that those figures had been “put together in September 2021”.

He said: “Since then the Bank of England has put up inflation figures, maxing out around 10 per cent in 2022-23, which is around the time that this would go out to tender. 

“Adding to that, construction cost increases are going to be above inflationary figures. The upshot is that it looks like there may be a £30 million hole in the budget.

“Is this really fully costed if it is known that the inflation figures come from before the latest Bank of England forecasts?”

READ MORE: Letter sent to Oxford County Council urging rejection of HIF1

He called for the county to hold off until after its capital budget review in September and to take into consideration up-to-date cost forecasts from the building industry at that point. 

Councillor Duncan Enright, the county’s cabinet member for travel and development strategy, said he had been “assured this is a fully-funded project”.

Addressing Mr Hicks, Mr Miller said the overall budget “includes a quantified risk and contingency fund and an allowance for inflation” but added that it “faces considerable inflationary risk”.

He said: “As a cabinet, in anticipating the conversation we will have in September about the prioritisation of our capital budget, we have been very clear that all schemes need at very minimum to live within their current financial envelope.

“When we discussed the grant determination agreement at our last meeting, we made very clear that this figure of £29.897 million was the maximum amount we could countenance from the council’s resources.

READ MORE: Council to take Didcot road scheme forward despite environmental concerns

“We are not prepared to put more money into it and consequently, to deliver the scheme it will be required for us to live within our means.

“In the face of the inflationary pressures you are describing, it will require value engineering by the project team that is already undertaking that work and potentially other measures to make sure we can live within our means.”

-

Read more from this author

This story was written by Gee Harland, she joined the team in 2022 as a senior multimedia reporter.

Gee covers Wallingford, Wantage and Didcot.

Get in touch with her by emailing: Gee.harland@newsquest.co.uk

Follow her on Twitter @Geeharland

A message from our Editor

Thank you for reading this story and supporting the Oxford Mail.

If you like what we do please consider getting a subscription for the Oxford Mail and in return we’ll give you unrestricted access with less adverts across our website from the latest news, investigations, features, and sport.

Follow us on Facebook, Twitter, Instagram and Tik Tok for more. 

You can also join the conversation in our Facebook groups: stay ahead of traffic alerts here, keep up to date with the latest from court here, share your favourite memories of Oxford here, get your daily dose of celebrity news here and take some time out with news that will make you smile. 

If you’ve got a story for our reporters, send us your news here. You can also list an event for free here.