A race against time to complete a massive and complex engineering project in Bicester has been completed on schedule.

After three years of planning, teams from Oxfordshire County Council, Cherwell District Council and Network Rail fitted two new railway underpasses on the Chiltern main line during a 100-hour window over the Easter period.

ALSO READ: Underbridge project starts in Bicester in bid to ease congestion

If the project had not met its deadline, the organisations would have had to wait another five to 10 years for the next opportunity to carry out the work, due to the heavy demands on the Network Rail calendar.

Oxford Mail: Part of the railway track was removed and replaced

The underbridges were inserted underneath the Marylebone/Aynho line north-west of Bicester between April 2-5, during the Easter bank holiday weekend.

The structures had been built off-site between October 2020 and March 2021, ready to be installed.

Owen Jenkins, Oxfordshire County Council’s director of growth and economy, said: “This successful operation was due to the extraordinary cooperation between the councils and Network Rail and its contractors.

"It is a testament to the hard work over the four days when the underbridges were put in place, as well as the high level of planning and collaborative work in the three years beforehand, covering the conception, design and pre-construction phases.”

The railway line was closed to allow for 21,000 tonnes of earth to be moved to make way for the underpasses. The teams removed and replaced 400 metres of railway track, and then drove the two new underpasses under the railway bridge with a huge transporter.

ALSO READ: Cherwell council closes Bicester house after noise complaints

Dave Penney, Network Rail’s central route director, said: “This £12.3 million investment in Bicester to create two new routes under the railway will not only benefit the flow of people and traffic, but also help both council’s regeneration vision. It’s a great example of how the rail industry can work in partnership with local authorities to unlock opportunities and growth for communities.”

Oxford Mail: Teams had 100 hours to complete the work

The new structures will connect areas of Bicester, which were previously cut off from each other by the railway line, and help open up the Eco-Town, including enabling the creation of up to 6,000 new homes and new community and recreational facilities.

The steel underbridge will accommodate the planned realignment of the A4095 (Howes Lane) and help to ease congestion, while the underpass will connect the new development for cyclists and pedestrians.

Robert Jolley, assistant director for growth and economy at Cherwell District Council, said: “This has been a key project for the development of Bicester Garden Town, and is an extraordinary example of multi-agency working bringing significant key players together with a clear, common purpose.

"It has also involved the productive use of both the growth deal and other funding, to deliver large-scale positive changes for our communities.

ALSO READ: Have your say in EWR consultation on Bicester level crossing

“Working with partners, we have unlocked important land to the north-west of Bicester, creating accessible walking and cycling routes for our future residents to enjoy.”

The project also provides upgraded rail track which will improve future journeys between London Marylebone and the Midlands.

Keep up to date with all the latest news on our website, or follow us on Facebook, Twitter and Instagram.